Sobha Central Phase 2

Construction progress

Sobha Central Phase 2 construction updates

Jebel Ali Village · Sobha L.L.C

Under constructionLast site inspection September 29, 2026 · 39 days ago
6.4%complete

When DLD first inspected the site on Aug 21, 2025, it was 0% complete. After 4 inspections it now stands at 6.4%.

That is about 0.5% more of the building completed each month on average.

First inspection · 0%Latest · 6.4%
Construction started
October 1, 2025
Completion date registered with DLD
June 30, 2030
Site inspections
4
Units
2,143
Buildings
4
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
4042

Latest site photos

September 29, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. September 29, 2026

    6 months after the previous inspection

    +4.1%6.4%
  2. March 28, 2026

    7 months after the previous inspection

    +2.3%2.3%
  3. August 21, 2025

    0 days after the previous inspection

    0%
  4. August 21, 2025

    First inspection

    0%

Thinking about Sobha Central Phase 2?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4042), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.