SLS Residences at The Palm Jumeirah Dubai

Construction progress

SLS Residences at The Palm Jumeirah Dubai construction updates

Palm Jumeirah · Roya Lifestyle Developments L.L.C

Under constructionLast site inspection May 18, 2026 · 6 months ago
60%complete

When DLD first inspected the site on Jun 2, 2023, it was 0% complete. After 9 inspections it now stands at 60%.

That is about 1.7% more of the building completed each month on average.

First inspection · 0%Latest · 60%
Construction started
August 1, 2023
Completion date registered with DLD
July 31, 2026
Site inspections
9
Units
114
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
2692

Latest site photos

May 18, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. May 18, 2026

    3 months after the previous inspection

    +18.4%60%
  2. February 19, 2026

    4 months after the previous inspection

    +3.6%41.6%
  3. November 4, 2025

    2 months after the previous inspection

    +8.7%38%
  4. August 21, 2025

    3 months after the previous inspection

    +10.7%29.2%
  5. May 16, 2025

    3 months after the previous inspection

    +5.5%18.5%
  6. February 20, 2025

    5 months after the previous inspection

    +8%13.1%
  7. September 12, 2024

    3 months after the previous inspection

    +3.6%5.1%
  8. June 3, 2024

    12 months after the previous inspection

    +1.6%1.6%
  9. June 2, 2023

    First inspection

    0%

Thinking about SLS Residences at The Palm Jumeirah Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2692), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.