Skyhills Residences 3 at JVC Dubai

Construction progress

Skyhills Residences 3 at JVC Dubai construction updates

JVC · Hre Real Estate Development L.L.C

Under constructionLast site inspection September 1, 2026 · 2 months ago
75.7%complete

When DLD first inspected the site on Jul 4, 2024, it was 20.3% complete. After 7 inspections it now stands at 75.7%.

That is about 2.1% more of the building completed each month on average.

First inspection · 20.3%Latest · 75.7%
Construction started
June 1, 2024
Completion date registered with DLD
June 1, 2026
Site inspections
7
Units
516
Buildings
2
Escrow bank
Sharjah Islamic Bank
DLD project no.
3058

Latest site photos

September 1, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 1, 2026

    4 months after the previous inspection

    +8.4%75.7%
  2. May 7, 2026

    3 months after the previous inspection

    +8.8%67.3%
  3. February 12, 2026

    3 months after the previous inspection

    +9.9%58.5%
  4. November 4, 2025

    3 months after the previous inspection

    +20.5%48.6%
  5. July 26, 2025

    4 months after the previous inspection

    +4.2%28.1%
  6. March 24, 2025

    9 months after the previous inspection

    +3.6%23.9%
  7. July 4, 2024

    First inspection

    20.3%

Thinking about Skyhills Residences 3 at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3058), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.