Skyhills Residences 2 at JVC Dubai

Construction progress

Skyhills Residences 2 at JVC Dubai construction updates

JVC · Hre Real Estate Development L.L.C

Under constructionLast site inspection October 15, 2026 · 23 days ago
96%complete

When DLD first inspected the site on Jul 4, 2024, it was 43.5% complete. After 9 inspections it now stands at 96%.

That is about 1.9% more of the building completed each month on average.

First inspection · 43.5%Latest · 96%
Construction started
June 1, 2024
Completion date registered with DLD
June 1, 2026
Site inspections
9
Units
529
Escrow bank
Sharjah Islamic Bank
DLD project no.
3057

Latest site photos

October 15, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 15, 2026

    3 months after the previous inspection

    +1%96%
  2. July 28, 2026

    39 days after the previous inspection

    +3.8%95%
  3. June 19, 2026

    43 days after the previous inspection

    +5.4%91.2%
  4. May 7, 2026

    3 months after the previous inspection

    +11.7%85.8%
  5. February 12, 2026

    3 months after the previous inspection

    +9.2%74.1%
  6. November 4, 2025

    4 months after the previous inspection

    +10.9%64.9%
  7. July 5, 2025

    3 months after the previous inspection

    +6%54%
  8. March 24, 2025

    9 months after the previous inspection

    +4.5%48%
  9. July 4, 2024

    First inspection

    43.5%

Thinking about Skyhills Residences 2 at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3057), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat