Construction progress

Skyhills Astra at Dubai Science Park - HRE Development construction updates

Dubai Science Park · Hre Real Estate Development L.L.C

Under constructionLast site inspection July 30, 2026 · 3 months ago
47.1%complete

When DLD first inspected the site on Jan 16, 2025, it was 32.8% complete. After 6 inspections it now stands at 47.1%.

That is about 0.8% more of the building completed each month on average.

First inspection · 32.8%Latest · 47.1%
Construction started
January 31, 2025
Completion date registered with DLD
June 30, 2028
Site inspections
6
Units
1,911
Buildings
3
Escrow bank
Sharjah Islamic Bank
DLD project no.
3480

Latest site photos

July 30, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. July 30, 2026

    3 months after the previous inspection

    +5%47.1%
  2. April 22, 2026

    3 months after the previous inspection

    +2.1%42.1%
  3. January 12, 2026

    4 months after the previous inspection

    +5.9%40%
  4. September 24, 2025

    0 days after the previous inspection

    34.1%
  5. September 24, 2025

    8 months after the previous inspection

    +1.3%34.1%
  6. January 16, 2025

    First inspection

    32.8%

Thinking about Skyhills Astra at Dubai Science Park - HRE Development?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3480), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.