Siraj Tower at Arjan Dubai

Construction progress

Siraj Tower at Arjan Dubai construction updates

Arjan Dubai · Al Madar Investment (L.L.C)

CompletedLast site inspection June 9, 2016 · 10 years ago
100%complete

DLD first inspected the site on Jun 4, 2013 at 25% complete, and recorded it as finished after 7 inspections, the last on Jun 9, 2016.

First inspection · 25%Latest · 100%
Construction started
October 14, 2008
Completion date registered with DLD
March 17, 2016
Site inspections
7
Units
374
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
181

Latest site photos

June 9, 2016

Progress over time

Progress over time
0%25%50%75%100%201420152016

Inspection history

  1. June 9, 2016

    8 months after the previous inspection

    +8.3%100%
  2. October 6, 2015

    5 months after the previous inspection

    +6.8%91.7%
  3. May 17, 2015

    2 months after the previous inspection

    +10.9%84.9%
  4. March 9, 2015

    5 months after the previous inspection

    +20%74%
  5. October 18, 2014

    12 months after the previous inspection

    +24%54%
  6. October 28, 2013

    5 months after the previous inspection

    +5%30%
  7. June 4, 2013

    First inspection

    25%

Thinking about Siraj Tower at Arjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 181), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.