Silena by AveNew Development at Dubai Islands

Construction progress

Silena by AveNew Development at Dubai Islands construction updates

Dubai Islands · Avenew Real Estate Development L.L.C

Under constructionLast site inspection November 3, 2026 · 4 days ago
5.7%complete

When DLD first inspected the site on Jun 24, 2025, it was 0% complete. After 5 inspections it now stands at 5.7%.

That is about 0.3% more of the building completed each month on average.

First inspection · 0%Latest · 5.7%
Construction started
December 1, 2025
Completion date registered with DLD
May 30, 2028
Site inspections
5
Units
137
Buildings
2
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3808

Latest site photos

November 3, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. November 3, 2026

    3 months after the previous inspection

    +1.8%5.7%
  2. July 31, 2026

    3 months after the previous inspection

    +2.2%3.8%
  3. May 1, 2026

    3 months after the previous inspection

    +1.6%1.6%
  4. January 29, 2026

    7 months after the previous inspection

    +0%0%
  5. June 24, 2025

    First inspection

    0%

Thinking about Silena by AveNew Development at Dubai Islands?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3808), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.