Serra at Ghaf Woods by Majid Al Futtaim

Construction progress

Serra at Ghaf Woods by Majid Al Futtaim construction updates

Dubailand · Majid Al Futtaim Ghaf Woods L.L.C

Under constructionLast site inspection August 17, 2026 · 3 months ago
42.1%complete

When DLD first inspected the site on May 9, 2024, it was 0% complete. After 7 inspections it now stands at 42.1%.

That is about 1.5% more of the building completed each month on average.

First inspection · 0%Latest · 42.1%
Construction started
December 27, 2024
Site inspections
7
Units
535
Buildings
10
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3076

Latest site photos

August 17, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 17, 2026

    0 days after the previous inspection

    42.1%
  2. August 17, 2026

    42 days after the previous inspection

    +3.6%42.1%
  3. July 6, 2026

    3 months after the previous inspection

    +14.4%38.4%
  4. March 26, 2026

    4 months after the previous inspection

    +6.5%24%
  5. November 26, 2025

    0 days after the previous inspection

    17.5%
  6. November 26, 2025

    19 months after the previous inspection

    +17.5%17.5%
  7. May 9, 2024

    First inspection

    0%

Thinking about Serra at Ghaf Woods by Majid Al Futtaim?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3076), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.