Construction progress

Serenity Mansions at Tilal Al Ghaf construction updates

Tilal Al Ghaf · Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C

Under constructionLast site inspection September 7, 2026 · 2 months ago
32.4%complete

When DLD first inspected the site on Jul 25, 2023, it was 0% complete. After 8 inspections it now stands at 32.4%.

That is about 0.9% more of the building completed each month on average.

First inspection · 0%Latest · 32.4%
Construction started
December 15, 2023
Site inspections
8
Units
110
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2718

Latest site photos

September 7, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 7, 2026

    4 months after the previous inspection

    +9.6%32.4%
  2. May 13, 2026

    2 months after the previous inspection

    +4.6%22.8%
  3. March 25, 2026

    2 months after the previous inspection

    +4.3%18.3%
  4. January 13, 2026

    3 months after the previous inspection

    +7.7%13.9%
  5. October 9, 2025

    15 days after the previous inspection

    +1%6.2%
  6. September 24, 2025

    7 months after the previous inspection

    +4.7%5.3%
  7. March 6, 2025

    19 months after the previous inspection

    +0.6%0.6%
  8. July 25, 2023

    First inspection

    0%

Thinking about Serenity Mansions at Tilal Al Ghaf?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2718), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.