Under constructionLast site inspection September 29, 2026 · 39 days ago
61.7%complete

When DLD first inspected the site on Aug 2, 2023, it was 0% complete. After 11 inspections it now stands at 61.7%.

That is about 1.6% more of the building completed each month on average.

First inspection · 0%Latest · 61.7%
Construction started
September 15, 2023
Site inspections
11
Units
184
Escrow bank
Mashreq Bank Psc
DLD project no.
2740

Latest site photos

September 29, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 29, 2026

    0 days after the previous inspection

    61.7%
  2. September 29, 2026

    0 days after the previous inspection

    61.7%
  3. September 29, 2026

    3 months after the previous inspection

    +9.6%61.7%
  4. June 29, 2026

    3 months after the previous inspection

    +12.9%52.1%
  5. March 18, 2026

    3 months after the previous inspection

    +9.1%39.2%
  6. December 17, 2025

    3 months after the previous inspection

    +12.3%30.1%
  7. October 1, 2025

    3 months after the previous inspection

    +6%17.8%
  8. June 18, 2025

    3 months after the previous inspection

    +6.3%11.9%
  9. March 7, 2025

    5 months after the previous inspection

    +5.4%5.6%
  10. September 26, 2024

    14 months after the previous inspection

    +0.2%0.2%
  11. August 2, 2023

    First inspection

    0%

Thinking about Serene Gardens at Al Furjan?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2740), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat