Serene Gardens 2 at Al Furjan

Construction progress

Serene Gardens 2 at Al Furjan construction updates

Al Furjan · Prescott Real Estate Development L.L.C

Under constructionLast site inspection September 29, 2026 · 39 days ago
70%complete

When DLD first inspected the site on Dec 19, 2023, it was 0% complete. After 9 inspections it now stands at 70%.

That is about 2.1% more of the building completed each month on average.

First inspection · 0%Latest · 70%
Construction started
January 1, 2024
Site inspections
9
Units
285
Escrow bank
United Bank Limited (Management Office)
DLD project no.
2872

Latest site photos

September 29, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 29, 2026

    3 months after the previous inspection

    +6.6%70%
  2. June 25, 2026

    3 months after the previous inspection

    +15%63.5%
  3. March 18, 2026

    3 months after the previous inspection

    +6.4%48.5%
  4. December 13, 2025

    2 months after the previous inspection

    +16.9%42%
  5. October 15, 2025

    3 months after the previous inspection

    +6.5%25.1%
  6. July 18, 2025

    4 months after the previous inspection

    +10.5%18.6%
  7. March 10, 2025

    5 months after the previous inspection

    +4.5%8.2%
  8. October 1, 2024

    9 months after the previous inspection

    +3.7%3.7%
  9. December 19, 2023

    First inspection

    0%

Thinking about Serene Gardens 2 at Al Furjan?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2872), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.