Seraph By Wadan

Construction progress

Seraph By Wadan construction updates

Dubailand · Wadan Real Estate Development L.L.C

Under constructionLast site inspection October 27, 2026 · 11 days ago
20.9%complete

When DLD first inspected the site on Sep 24, 2025, it was 0% complete. After 4 inspections it now stands at 20.9%.

That is about 1.6% more of the building completed each month on average.

First inspection · 0%Latest · 20.9%
Construction started
December 15, 2025
Completion date registered with DLD
December 15, 2027
Site inspections
4
Units
190
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
4109

Latest site photos

October 27, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 27, 2026

    3 months after the previous inspection

    +9.8%20.9%
  2. July 22, 2026

    3 months after the previous inspection

    +9.4%11.1%
  3. April 22, 2026

    7 months after the previous inspection

    +1.7%1.7%
  4. September 24, 2025

    First inspection

    0%

Thinking about Seraph By Wadan?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4109), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.