Seaside by Prestige One

Construction progress

Seaside by Prestige One construction updates

Dubai Islands · Prestige The Seaside Real Estate Development L.L.C

Under constructionLast site inspection November 2, 2026 · 5 days ago
53%complete

When DLD first inspected the site on Jun 6, 2024, it was 0% complete. After 7 inspections it now stands at 53%.

That is about 1.8% more of the building completed each month on average.

First inspection · 0%Latest · 53%
Construction started
July 25, 2024
Completion date registered with DLD
December 25, 2026
Site inspections
7
Units
121
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3119

Latest site photos

November 2, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. November 2, 2026

    3 months after the previous inspection

    +10%53%
  2. July 30, 2026

    3 months after the previous inspection

    +9.7%43%
  3. April 30, 2026

    3 months after the previous inspection

    +13.2%33.3%
  4. January 29, 2026

    8 months after the previous inspection

    +14.5%20.1%
  5. May 30, 2025

    6 months after the previous inspection

    +5.6%5.7%
  6. December 13, 2024

    6 months after the previous inspection

    +0%0%
  7. June 6, 2024

    First inspection

    0%

Thinking about Seaside by Prestige One?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3119), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.