Seapoint at Emaar Beachfront

Construction progress

Seapoint at Emaar Beachfront construction updates

Emaar Beachfront · Emaar Development P.J.S.C.

Under constructionLast site inspection June 24, 2026 · 4 months ago
36.8%complete

When DLD first inspected the site on Apr 7, 2023, it was 0% complete. After 9 inspections it now stands at 36.8%.

That is about 1% more of the building completed each month on average.

First inspection · 0%Latest · 36.8%
Construction started
September 12, 2023
Completion date registered with DLD
March 31, 2028
Site inspections
9
Units
674
Buildings
3
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2633

Latest site photos

June 24, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. June 24, 2026

    5 months after the previous inspection

    +11.6%36.8%
  2. February 4, 2026

    4 months after the previous inspection

    +9.2%25.2%
  3. October 3, 2025

    4 months after the previous inspection

    +6.2%16%
  4. May 23, 2025

    4 months after the previous inspection

    +3.2%9.8%
  5. January 29, 2025

    4 months after the previous inspection

    +1.1%6.6%
  6. October 10, 2024

    4 months after the previous inspection

    +5.1%5.5%
  7. June 5, 2024

    7 months after the previous inspection

    +0.3%0.4%
  8. November 8, 2023

    7 months after the previous inspection

    +0.2%0.2%
  9. April 7, 2023

    First inspection

    0%

Thinking about Seapoint at Emaar Beachfront?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2633), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.