Construction progress

Sapphire 32 Residence at JVC construction updates

JVC · Dar Al Karama Real Estate L.L.C

Under constructionLast site inspection July 10, 2026 · 4 months ago
62.3%complete

When DLD first inspected the site on Aug 31, 2023, it was 0% complete. After 8 inspections it now stands at 62.3%.

That is about 1.8% more of the building completed each month on average.

First inspection · 0%Latest · 62.3%
Construction started
October 1, 2023
Completion date registered with DLD
December 15, 2026
Site inspections
8
Units
232
Escrow bank
Sharjah Islamic Bank
DLD project no.
2757

Latest site photos

July 10, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. July 10, 2026

    4 months after the previous inspection

    +0.4%62.3%
  2. March 23, 2026

    4 months after the previous inspection

    +27.8%61.9%

    No photos were published for this inspection.

  3. November 27, 2025

    3 months after the previous inspection

    +11.3%34%
  4. August 18, 2025

    4 months after the previous inspection

    +8.3%22.8%
  5. April 24, 2025

    4 months after the previous inspection

    +6.5%14.5%
  6. January 2, 2025

    3 months after the previous inspection

    +5.5%8%
  7. September 30, 2024

    13 months after the previous inspection

    +2.5%2.5%
  8. August 31, 2023

    First inspection

    0%

Thinking about Sapphire 32 Residence at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2757), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.