Samana Waves at JVC

Construction progress

Samana Waves at JVC construction updates

JVC · Samana Si Holding Limited Dubai Branch

Under constructionLast site inspection October 16, 2026 · 22 days ago
90.6%complete

When DLD first inspected the site on Dec 5, 2022, it was 0% complete. After 10 inspections it now stands at 90.6%.

That is about 2% more of the building completed each month on average.

First inspection · 0%Latest · 90.6%
Construction started
July 1, 2022
Completion date registered with DLD
April 15, 2026
Site inspections
10
Units
197
Escrow bank
Mashreq Bank Psc
DLD project no.
2345

Latest site photos

October 16, 2026

Progress over time

Progress over time
0%25%50%75%100%2023202420252026

Inspection history

  1. October 16, 2026

    4 months after the previous inspection

    +0.5%90.6%
  2. June 19, 2026

    4 months after the previous inspection

    +13.3%90.1%
  3. February 5, 2026

    3 months after the previous inspection

    +3.7%76.7%
  4. November 20, 2025

    4 months after the previous inspection

    +18.6%73%
  5. July 14, 2025

    5 months after the previous inspection

    +14.3%54.4%
  6. January 31, 2025

    3 months after the previous inspection

    +12.9%40.1%
  7. November 13, 2024

    6 months after the previous inspection

    +16.9%27.2%
  8. May 14, 2024

    14 months after the previous inspection

    +6.6%10.2%
  9. March 15, 2023

    3 months after the previous inspection

    +3.6%3.6%
  10. December 5, 2022

    First inspection

    0%

Thinking about Samana Waves at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2345), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.