Samana Waves 2 at JVC

Construction progress

Samana Waves 2 at JVC construction updates

JVC · Samana Si Holding Limited Dubai Branch

Under constructionLast site inspection October 2, 2026 · 36 days ago
52.1%complete

When DLD first inspected the site on Feb 7, 2023, it was 0% complete. After 8 inspections it now stands at 52.1%.

That is about 1.2% more of the building completed each month on average.

First inspection · 0%Latest · 52.1%
Construction started
September 21, 2023
Completion date registered with DLD
March 20, 2026
Site inspections
8
Units
173
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2574

Latest site photos

October 2, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. October 2, 2026

    3 months after the previous inspection

    +4.8%52.1%
  2. June 19, 2026

    4 months after the previous inspection

    +11.9%47.3%
  3. February 11, 2026

    2 months after the previous inspection

    +10.2%35.4%
  4. November 27, 2025

    0 days after the previous inspection

    25.2%
  5. November 27, 2025

    4 months after the previous inspection

    +10.8%25.2%
  6. July 29, 2025

    6 months after the previous inspection

    +9.4%14.4%
  7. January 24, 2025

    24 months after the previous inspection

    +5%5%
  8. February 7, 2023

    First inspection

    0%

Thinking about Samana Waves 2 at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2574), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.