Samana Resorts at Dubai Production City

Construction progress

Samana Resorts at Dubai Production City construction updates

Dubai Production City · Samana International Real Estate Development L.L.C

Under constructionLast site inspection October 22, 2026 · 16 days ago
5.9%complete

When DLD first inspected the site on Mar 7, 2024, it was 0% complete. After 6 inspections it now stands at 5.9%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 5.9%
Construction started
May 1, 2025
Completion date registered with DLD
May 30, 2028
Site inspections
6
Units
969
Buildings
4
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2895

Latest site photos

October 22, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 22, 2026

    4 months after the previous inspection

    +0%5.9%
  2. June 23, 2026

    3 months after the previous inspection

    +1.4%5.8%
  3. April 3, 2026

    5 months after the previous inspection

    +1.4%4.4%
  4. November 3, 2025

    5 months after the previous inspection

    +1%3%
  5. June 17, 2025

    15 months after the previous inspection

    +2%2%
  6. March 7, 2024

    First inspection

    0%

Thinking about Samana Resorts at Dubai Production City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2895), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat