Samana Portofino at Dubai Production City

Construction progress

Samana Portofino at Dubai Production City construction updates

Dubai Production City · Samana International Real Estate Development L.L.C

Under constructionLast site inspection September 29, 2026 · 39 days ago
60.1%complete

When DLD first inspected the site on Aug 28, 2023, it was 0% complete. After 7 inspections it now stands at 60.1%.

That is about 1.6% more of the building completed each month on average.

First inspection · 0%Latest · 60.1%
Construction started
March 1, 2024
Site inspections
7
Units
226
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2750

Latest site photos

September 29, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 29, 2026

    4 months after the previous inspection

    +12.8%60.1%
  2. May 19, 2026

    4 months after the previous inspection

    +11.4%47.2%
  3. January 26, 2026

    2 months after the previous inspection

    +13.4%35.8%
  4. November 20, 2025

    4 months after the previous inspection

    +11.7%22.4%
  5. July 25, 2025

    6 months after the previous inspection

    +8.8%10.8%
  6. February 6, 2025

    17 months after the previous inspection

    +2%2%
  7. August 28, 2023

    First inspection

    0%

Thinking about Samana Portofino at Dubai Production City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2750), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.