Samana Park Meadows at DLRC, Dubai

Construction progress

Samana Park Meadows at DLRC, Dubai construction updates

Dubailand · Samana International Real Estate Development L.L.C

Under constructionLast site inspection October 1, 2026 · 37 days ago
38%complete

When DLD first inspected the site on Mar 4, 2024, it was 0% complete. After 7 inspections it now stands at 38%.

That is about 1.2% more of the building completed each month on average.

First inspection · 0%Latest · 38%
Construction started
August 1, 2024
Completion date registered with DLD
August 31, 2027
Site inspections
7
Units
221
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2896

Latest site photos

October 1, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 1, 2026

    3 months after the previous inspection

    +10.8%38%
  2. June 18, 2026

    4 months after the previous inspection

    +9.9%27.3%
  3. February 3, 2026

    3 months after the previous inspection

    +8.8%17.4%
  4. October 23, 2025

    3 months after the previous inspection

    +4.2%8.6%
  5. July 16, 2025

    7 months after the previous inspection

    +2.4%4.4%
  6. December 25, 2024

    10 months after the previous inspection

    +2%2%
  7. March 4, 2024

    First inspection

    0%

Thinking about Samana Park Meadows at DLRC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2896), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.