Samana Mykonos Signature at Arjan, Dubailand

Construction progress

Samana Mykonos Signature at Arjan, Dubailand construction updates

Arjan Dubai · Samana International Real Estate Development L.L.C

Under constructionLast site inspection October 12, 2026 · 26 days ago
86%complete

When DLD first inspected the site on Mar 2, 2023, it was 0% complete. After 9 inspections it now stands at 86%.

That is about 2% more of the building completed each month on average.

First inspection · 0%Latest · 86%
Construction started
October 1, 2023
Completion date registered with DLD
April 30, 2026
Site inspections
9
Units
300
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2587

Latest site photos

October 12, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. October 12, 2026

    5 months after the previous inspection

    +5.5%86%
  2. May 14, 2026

    4 months after the previous inspection

    +7.8%80.5%
  3. January 22, 2026

    4 months after the previous inspection

    +23.2%72.7%
  4. October 2, 2025

    2 months after the previous inspection

    +5%49.4%
  5. July 29, 2025

    4 months after the previous inspection

    +13.5%44.5%
  6. March 26, 2025

    5 months after the previous inspection

    +16%31%
  7. October 23, 2024

    6 months after the previous inspection

    +13.2%15.1%
  8. May 8, 2024

    14 months after the previous inspection

    +1.9%1.9%
  9. March 2, 2023

    First inspection

    0%

Thinking about Samana Mykonos Signature at Arjan, Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2587), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.