Samana Mykonos at Dubai Studio City

Construction progress

Samana Mykonos at Dubai Studio City construction updates

Dubai Studio City · Samana International Real Estate Development L.L.C

Under constructionLast site inspection September 29, 2026 · 39 days ago
91.1%complete

When DLD first inspected the site on Jan 20, 2023, it was 0% complete. After 9 inspections it now stands at 91.1%.

That is about 2.1% more of the building completed each month on average.

First inspection · 0%Latest · 91.1%
Construction started
June 30, 2023
Completion date registered with DLD
April 30, 2026
Site inspections
9
Units
198
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2561

Latest site photos

September 29, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. September 29, 2026

    4 months after the previous inspection

    +10.2%91.1%
  2. May 20, 2026

    3 months after the previous inspection

    +14.3%81%
  3. February 4, 2026

    2 months after the previous inspection

    +1.7%66.7%
  4. November 24, 2025

    4 months after the previous inspection

    +9.6%65%
  5. July 16, 2025

    5 months after the previous inspection

    +17%55.4%
  6. February 17, 2025

    4 months after the previous inspection

    +15.3%38.4%
  7. October 31, 2024

    6 months after the previous inspection

    +12.4%23.1%
  8. May 7, 2024

    16 months after the previous inspection

    +10.7%10.7%
  9. January 20, 2023

    First inspection

    0%

Thinking about Samana Mykonos at Dubai Studio City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2561), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.