Samana Miami at Jumeirah Village Circle

Construction progress

Samana Miami at Jumeirah Village Circle construction updates

JVC · Samana Si Holding Limited Dubai Branch

CompletedLast site inspection June 1, 2026 · 5 months ago
100%complete

DLD first inspected the site on Jun 22, 2023 at 1.7% complete, and recorded it as finished after 7 inspections, the last on Jun 1, 2026.

First inspection · 1.7%Latest · 100%
Construction started
January 1, 2023
Completion date registered with DLD
December 1, 2024
Site inspections
7
Units
93
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2433

Latest site photos

June 1, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. June 1, 2026

    10 months after the previous inspection

    +5.4%100%
  2. July 17, 2025

    5 months after the previous inspection

    +16%94.6%
  3. January 31, 2025

    4 months after the previous inspection

    +27.7%78.6%
  4. September 21, 2024

    6 months after the previous inspection

    +14.5%50.9%
  5. April 1, 2024

    7 months after the previous inspection

    +24%36.5%
  6. September 12, 2023

    3 months after the previous inspection

    +10.8%12.5%
  7. June 22, 2023

    First inspection

    1.7%

Thinking about Samana Miami at Jumeirah Village Circle?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2433), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.