Samana Lake Views 2 at Dubai Production City

Construction progress

Samana Lake Views 2 at Dubai Production City construction updates

Dubai Production City · Samana Signature Real Estate Developments L.L.C

Under constructionLast site inspection October 28, 2026 · 10 days ago
12%complete

When DLD first inspected the site on May 8, 2024, it was 0% complete. After 7 inspections it now stands at 12%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 12%
Construction started
June 1, 2024
Site inspections
7
Units
548
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
3087

Latest site photos

October 28, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 28, 2026

    5 months after the previous inspection

    +3.1%12%
  2. June 10, 2026

    4 months after the previous inspection

    +1.4%8.9%
  3. February 5, 2026

    3 months after the previous inspection

    +3.3%7.5%
  4. November 3, 2025

    4 months after the previous inspection

    +0.4%4.1%
  5. July 2, 2025

    5 months after the previous inspection

    +3.5%3.8%
  6. January 29, 2025

    9 months after the previous inspection

    +0.3%0.3%
  7. May 8, 2024

    First inspection

    0%

Thinking about Samana Lake Views 2 at Dubai Production City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3087), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.