Samana Ibiza at Dubailand Dubai

Construction progress

Samana Ibiza at Dubailand Dubai construction updates

Dubailand · Samana International Real Estate Development L.L.C

Under constructionLast site inspection October 21, 2026 · 17 days ago
5.5%complete

When DLD first inspected the site on Mar 14, 2024, it was 0% complete. After 6 inspections it now stands at 5.5%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 5.5%
Construction started
August 1, 2024
Completion date registered with DLD
February 28, 2028
Site inspections
6
Units
455
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2897

Latest site photos

October 21, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 21, 2026

    4 months after the previous inspection

    +2.4%5.5%
  2. June 18, 2026

    4 months after the previous inspection

    +0.7%3.1%
  3. February 12, 2026

    3 months after the previous inspection

    +1.6%2.4%
  4. November 24, 2025

    3 months after the previous inspection

    +0.6%0.8%
  5. August 21, 2025

    17 months after the previous inspection

    +0.2%0.2%
  6. March 14, 2024

    First inspection

    0%

Thinking about Samana Ibiza at Dubailand Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2897), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.