Samana Barari Views at Majan

Construction progress

Samana Barari Views at Majan construction updates

Majan · Samana International Real Estate Development L.L.C

Under constructionLast site inspection October 28, 2026 · 10 days ago
32.4%complete

When DLD first inspected the site on Nov 1, 2023, it was 0% complete. After 7 inspections it now stands at 32.4%.

That is about 0.9% more of the building completed each month on average.

First inspection · 0%Latest · 32.4%
Construction started
February 1, 2024
Completion date registered with DLD
March 31, 2027
Site inspections
7
Units
669
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2835

Latest site photos

October 28, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. October 28, 2026

    5 months after the previous inspection

    +5.6%32.4%
  2. May 19, 2026

    4 months after the previous inspection

    +2.9%26.8%
  3. January 28, 2026

    3 months after the previous inspection

    +9.2%23.9%
  4. October 30, 2025

    4 months after the previous inspection

    +4.1%14.8%
  5. July 3, 2025

    8 months after the previous inspection

    +5.4%10.7%
  6. November 14, 2024

    12 months after the previous inspection

    +5.3%5.3%
  7. November 1, 2023

    First inspection

    0%

Thinking about Samana Barari Views at Majan?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2835), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.