Samana Barari Lagoons at Majan, Dubai

Construction progress

Samana Barari Lagoons at Majan, Dubai construction updates

Majan · Samana Signature Real Estate Developments L.L.C

Under constructionLast site inspection October 20, 2026 · 18 days ago
16.5%complete

When DLD first inspected the site on Nov 21, 2024, it was 0% complete. After 7 inspections it now stands at 16.5%.

That is about 0.7% more of the building completed each month on average.

First inspection · 0%Latest · 16.5%
Construction started
April 1, 2025
Completion date registered with DLD
March 31, 2028
Site inspections
7
Units
601
Escrow bank
The National Bank Of Fujairah P S C
DLD project no.
3422

Latest site photos

October 20, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 20, 2026

    5 months after the previous inspection

    +4.7%16.5%
  2. June 2, 2026

    4 months after the previous inspection

    +2%11.8%
  3. February 3, 2026

    3 months after the previous inspection

    +4%9.9%
  4. October 27, 2025

    4 months after the previous inspection

    +1.9%5.9%
  5. July 3, 2025

    4 months after the previous inspection

    +2.3%4%
  6. March 10, 2025

    4 months after the previous inspection

    +1.8%1.8%
  7. November 21, 2024

    First inspection

    0%

Thinking about Samana Barari Lagoons at Majan, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3422), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.