Samana Avenue at Dubai Land Residence Complex

Construction progress

Samana Avenue at Dubai Land Residence Complex construction updates

Dubai Land Residence Complex (DLRC) · Samana International Real Estate Development L.L.C

Under constructionLast site inspection October 1, 2026 · 37 days ago
31.8%complete

When DLD first inspected the site on Mar 4, 2024, it was 0% complete. After 6 inspections it now stands at 31.8%.

That is about 1% more of the building completed each month on average.

First inspection · 0%Latest · 31.8%
Construction started
July 1, 2024
Completion date registered with DLD
December 31, 2027
Site inspections
6
Units
165
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2898

Latest site photos

October 1, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 1, 2026

    3 months after the previous inspection

    +10.3%31.8%
  2. June 18, 2026

    4 months after the previous inspection

    +9.7%21.5%
  3. February 10, 2026

    4 months after the previous inspection

    +8.8%11.7%
  4. October 16, 2025

    4 months after the previous inspection

    +1%2.9%
  5. June 17, 2025

    15 months after the previous inspection

    +1.9%1.9%
  6. March 4, 2024

    First inspection

    0%

Thinking about Samana Avenue at Dubai Land Residence Complex?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2898), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat