Rove Home at Downtown Dubai

Construction progress

Rove Home at Downtown Dubai construction updates

Downtown Dubai · Irth Development L.L.C

Under constructionLast site inspection June 9, 2026 · 5 months ago
62.7%complete

When DLD first inspected the site on Aug 22, 2023, it was 0% complete. After 10 inspections it now stands at 62.7%.

That is about 1.9% more of the building completed each month on average.

First inspection · 0%Latest · 62.7%
Construction started
September 30, 2023
Completion date registered with DLD
April 30, 2026
Site inspections
10
Units
349
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
2738

Latest site photos

June 9, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. June 9, 2026

    4 months after the previous inspection

    +9.5%62.7%
  2. February 16, 2026

    3 months after the previous inspection

    +13%53.2%
  3. November 3, 2025

    5 months after the previous inspection

    +13.6%40.2%
  4. June 19, 2025

    2 months after the previous inspection

    +7.9%26.6%
  5. April 4, 2025

    3 months after the previous inspection

    +5.3%18.7%
  6. January 6, 2025

    3 months after the previous inspection

    +6.3%13.4%
  7. October 16, 2024

    4 months after the previous inspection

    +1.5%7.1%
  8. June 3, 2024

    5 months after the previous inspection

    +5.4%5.6%
  9. December 27, 2023

    4 months after the previous inspection

    +0.2%0.2%
  10. August 22, 2023

    First inspection

    0%

Thinking about Rove Home at Downtown Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2738), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.