Rosemont Residences at JVT Dubai

Construction progress

Rosemont Residences at JVT Dubai construction updates

JVT · Ellington Properties Development L.L.C

Under constructionLast site inspection November 2, 2026 · 5 days ago
68.4%complete

When DLD first inspected the site on Apr 3, 2024, it was 0% complete. After 6 inspections it now stands at 68.4%.

That is about 2.2% more of the building completed each month on average.

First inspection · 0%Latest · 68.4%
Construction started
March 14, 2024
Site inspections
6
Units
49
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2993

Latest site photos

November 2, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. November 2, 2026

    5 months after the previous inspection

    +25.5%68.4%
  2. June 8, 2026

    4 months after the previous inspection

    +19.3%42.9%
  3. February 2, 2026

    4 months after the previous inspection

    +10.5%23.5%
  4. September 23, 2025

    4 months after the previous inspection

    +5.8%13.1%
  5. June 3, 2025

    14 months after the previous inspection

    +7.3%7.3%
  6. April 3, 2024

    First inspection

    0%

Thinking about Rosemont Residences at JVT Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2993), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.