Rosalia Residences at Al Furjan Dubai

Construction progress

Rosalia Residences at Al Furjan Dubai construction updates

Al Furjan · Deyaar Development (P.J.S.C)

Under constructionLast site inspection October 29, 2026 · 9 days ago
93%complete

When DLD first inspected the site on Jan 8, 2024, it was 0% complete. After 8 inspections it now stands at 93%.

That is about 2.8% more of the building completed each month on average.

First inspection · 0%Latest · 93%
Construction started
September 30, 2023
Site inspections
8
Units
118
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2911

Latest site photos

October 29, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 29, 2026

    3 months after the previous inspection

    +11%93%
  2. August 5, 2026

    5 months after the previous inspection

    +11%82%
  3. March 18, 2026

    4 months after the previous inspection

    +7.4%71.1%
  4. November 27, 2025

    6 months after the previous inspection

    +18.2%63.7%
  5. May 26, 2025

    4 months after the previous inspection

    +10.1%45.5%
  6. February 5, 2025

    6 months after the previous inspection

    +18.6%35.4%
  7. July 23, 2024

    6 months after the previous inspection

    +16.8%16.8%
  8. January 8, 2024

    First inspection

    0%

Thinking about Rosalia Residences at Al Furjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2911), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.