Riviera Chalet at JVC

Construction progress

Riviera Chalet at JVC construction updates

JVC · Riviera Azure Properties Development

Under constructionLast site inspection November 4, 2026 · 2 days ago
90%complete

When DLD first inspected the site on Aug 1, 2023, it was 0% complete. After 8 inspections it now stands at 90%.

That is about 2.3% more of the building completed each month on average.

First inspection · 0%Latest · 90%
Construction started
June 1, 2023
Site inspections
8
Units
57
Escrow bank
United Bank Limited (Management Office)
DLD project no.
2737

Latest site photos

November 4, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. November 4, 2026

    4 months after the previous inspection

    +15.1%90%
  2. July 15, 2026

    4 months after the previous inspection

    +13.4%74.9%
  3. March 26, 2026

    5 months after the previous inspection

    +21.8%61.5%
  4. November 7, 2025

    0 days after the previous inspection

    39.6%
  5. November 7, 2025

    7 months after the previous inspection

    +22.1%39.6%
  6. March 27, 2025

    5 months after the previous inspection

    +14.8%17.5%
  7. October 22, 2024

    15 months after the previous inspection

    +2.7%2.7%
  8. August 1, 2023

    First inspection

    0%

Thinking about Riviera Chalet at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2737), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.