Riva Residence at Dubai Maritime City

Construction progress

Riva Residence at Dubai Maritime City construction updates

Dubai Maritime City · Vakson First Property Development L.L.C

CompletedLast site inspection December 22, 2025 · 11 months ago
100%complete

DLD first inspected the site on Apr 29, 2024 at 30.3% complete, and recorded it as finished after 4 inspections, the last on Dec 22, 2025.

First inspection · 30.3%Latest · 100%
Construction started
November 1, 2022
Completion date registered with DLD
September 25, 2025
Site inspections
4
Units
155
Escrow bank
United Bank Limited (Management Office)
DLD project no.
3034

Latest site photos

December 22, 2025

Progress over time

Progress over time
0%25%50%75%100%2025

Inspection history

  1. December 22, 2025

    5 months after the previous inspection

    +11.1%100%
  2. July 29, 2025

    9 months after the previous inspection

    +35.3%88.9%
  3. October 29, 2024

    6 months after the previous inspection

    +23.3%53.6%
  4. April 29, 2024

    First inspection

    30.3%

Thinking about Riva Residence at Dubai Maritime City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3034), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.