Construction progress
Dubai Maritime City · Vakson First Property Development L.L.C
DLD first inspected the site on Apr 29, 2024 at 30.3% complete, and recorded it as finished after 4 inspections, the last on Dec 22, 2025.
December 22, 2025
5 months after the previous inspection
9 months after the previous inspection
6 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3034), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.