Rise Residence at JVC

Construction progress

Rise Residence at JVC construction updates

JVC · S And S Real Estate Development L.L.C

CompletedLast site inspection January 5, 2026 · 10 months ago
100%complete

DLD first inspected the site on Jul 25, 2023 at 0% complete, and recorded it as finished after 6 inspections, the last on Jan 5, 2026.

First inspection · 0%Latest · 100%
Construction started
August 25, 2023
Completion date registered with DLD
August 31, 2025
Site inspections
6
Units
174
Escrow bank
Sharjah Islamic Bank
DLD project no.
2731

Latest site photos

January 5, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. January 5, 2026

    8 months after the previous inspection

    +18.9%100%
  2. May 15, 2025

    4 months after the previous inspection

    +19.9%81.1%
  3. January 27, 2025

    3 months after the previous inspection

    +16.8%61.2%
  4. November 4, 2024

    6 months after the previous inspection

    +24.4%44.4%
  5. May 2, 2024

    9 months after the previous inspection

    +20%20%
  6. July 25, 2023

    First inspection

    0%

Thinking about Rise Residence at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2731), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.