Construction progress
Business Bay · Deyaar Development (P.J.S.C)
DLD first inspected the site on Feb 2, 2022 at 6.4% complete, and recorded it as finished after 12 inspections, the last on Apr 29, 2026.
April 29, 2026
6 days after the previous inspection
16 days after the previous inspection
10 months after the previous inspection
3 months after the previous inspection
7 months after the previous inspection
4 months after the previous inspection
7 months after the previous inspection
4 months after the previous inspection
4 months after the previous inspection
4 months after the previous inspection
6 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2270), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.