Reef 1000 at DLRC Dubailand

Construction progress

Reef 1000 at DLRC Dubailand construction updates

Dubai Land Residence Complex (DLRC) · Reef Luxury Development L.L.C

Under constructionLast site inspection October 5, 2026 · 33 days ago
67.2%complete

When DLD first inspected the site on Aug 8, 2024, it was 0% complete. After 7 inspections it now stands at 67.2%.

That is about 2.6% more of the building completed each month on average.

First inspection · 0%Latest · 67.2%
Construction started
November 1, 2024
Completion date registered with DLD
December 30, 2026
Site inspections
7
Units
126
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3219

Latest site photos

October 5, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 5, 2026

    3 months after the previous inspection

    +17.2%67.2%
  2. July 14, 2026

    3 months after the previous inspection

    +19.2%50%
  3. April 24, 2026

    2 months after the previous inspection

    +7.7%30.8%
  4. February 9, 2026

    4 months after the previous inspection

    +5.3%23.1%
  5. October 7, 2025

    3 months after the previous inspection

    +7.6%17.8%
  6. July 9, 2025

    11 months after the previous inspection

    +10.2%10.2%
  7. August 8, 2024

    First inspection

    0%

Thinking about Reef 1000 at DLRC Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3219), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.