Pristine by Zoya at Al Furjan

Construction progress

Pristine by Zoya at Al Furjan construction updates

Al Furjan · Zoya One Real Estate Developments L.L.C

Under constructionLast site inspection August 20, 2026 · 3 months ago
58.4%complete

When DLD first inspected the site on May 23, 2024, it was 0% complete. After 7 inspections it now stands at 58.4%.

That is about 2.2% more of the building completed each month on average.

First inspection · 0%Latest · 58.4%
Construction started
September 1, 2024
Completion date registered with DLD
January 1, 2027
Site inspections
7
Units
73
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
3069

Latest site photos

August 20, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 20, 2026

    3 months after the previous inspection

    +17.1%58.4%
  2. May 7, 2026

    22 days after the previous inspection

    +16.1%41.2%
  3. April 15, 2026

    3 months after the previous inspection

    +3.6%25.1%
  4. January 22, 2026

    2 months after the previous inspection

    +8.6%21.6%
  5. November 26, 2025

    5 months after the previous inspection

    +13%13%
  6. July 1, 2025

    13 months after the previous inspection

    0%
  7. May 23, 2024

    First inspection

    0%

Thinking about Pristine by Zoya at Al Furjan?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3069), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.