Construction progress
Al Furjan · Zoya One Real Estate Developments L.L.C
When DLD first inspected the site on May 23, 2024, it was 0% complete. After 7 inspections it now stands at 58.4%.
That is about 2.2% more of the building completed each month on average.
August 20, 2026
3 months after the previous inspection
22 days after the previous inspection
3 months after the previous inspection
2 months after the previous inspection
5 months after the previous inspection
13 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3069), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.