Plagette 32 at Tilal Al Ghaf, Dubai

Construction progress

Plagette 32 at Tilal Al Ghaf, Dubai construction updates

Tilal Al Ghaf · Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C

Under constructionLast site inspection August 13, 2026 · 3 months ago
60.6%complete

When DLD first inspected the site on Oct 26, 2023, it was 0% complete. After 7 inspections it now stands at 60.6%.

That is about 1.8% more of the building completed each month on average.

First inspection · 0%Latest · 60.6%
Construction started
June 15, 2024
Site inspections
7
Units
32
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2827

Latest site photos

August 13, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 13, 2026

    36 days after the previous inspection

    +7.2%60.6%
  2. July 8, 2026

    3 months after the previous inspection

    +8%53.3%
  3. March 30, 2026

    2 months after the previous inspection

    +3.3%45.3%
  4. January 26, 2026

    5 months after the previous inspection

    +34.9%42%
  5. September 8, 2025

    7 months after the previous inspection

    +5.3%7.1%
  6. January 24, 2025

    15 months after the previous inspection

    +1.8%1.8%
  7. October 26, 2023

    First inspection

    0%

Thinking about Plagette 32 at Tilal Al Ghaf, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2827), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.