PG Maison at Al Furjan, Dubai

Construction progress

PG Maison at Al Furjan, Dubai construction updates

Al Furjan · Pg Maison Real Estate Development L.L.C

Under constructionLast site inspection August 5, 2026 · 3 months ago
10%complete

When DLD first inspected the site on Jun 27, 2024, it was 0% complete. After 6 inspections it now stands at 10%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 10%
Construction started
February 1, 2025
Completion date registered with DLD
December 31, 2027
Site inspections
6
Units
85
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3151

Latest site photos

August 5, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 5, 2026

    5 months after the previous inspection

    +3.6%10%
  2. March 5, 2026

    2 months after the previous inspection

    +0.9%6.5%
  3. December 25, 2025

    4 months after the previous inspection

    +4.1%5.6%
  4. September 8, 2025

    4 months after the previous inspection

    +1.5%1.5%
  5. May 1, 2025

    10 months after the previous inspection

    +0%0%
  6. June 27, 2024

    First inspection

    0%

Thinking about PG Maison at Al Furjan, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3151), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.