Petalz by Danube

Construction progress

Petalz by Danube construction updates

International City Dubai · Danube Properties Development L.L.C

CompletedLast site inspection October 28, 2025 · 12 months ago
100%complete

DLD first inspected the site on Oct 24, 2022 at 0% complete, and recorded it as finished after 11 inspections, the last on Oct 28, 2025.

First inspection · 0%Latest · 100%
Construction started
March 1, 2023
Completion date registered with DLD
December 31, 2025
Site inspections
11
Units
355
Buildings
2
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
2495

Latest site photos

October 28, 2025

Progress over time

Progress over time
0%25%50%75%100%202320242025

Inspection history

  1. October 28, 2025

    21 days after the previous inspection

    +1.2%100%
  2. October 7, 2025

    13 days after the previous inspection

    +3.5%98.8%
  3. September 24, 2025

    4 months after the previous inspection

    +17.7%95.3%
  4. May 31, 2025

    5 months after the previous inspection

    +36.4%77.6%
  5. January 9, 2025

    6 months after the previous inspection

    +29.9%41.3%
  6. July 22, 2024

    0 days after the previous inspection

    11.4%
  7. July 22, 2024

    4 months after the previous inspection

    +5.2%11.4%
  8. March 20, 2024

    4 months after the previous inspection

    +4.5%6.2%
  9. November 7, 2023

    5 months after the previous inspection

    +1.7%1.7%
  10. June 5, 2023

    7 months after the previous inspection

    +0%0%
  11. October 24, 2022

    First inspection

    0%

Thinking about Petalz by Danube?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2495), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.