Peninsula Two at Business Bay by Select Group

Construction progress

Peninsula Two at Business Bay by Select Group construction updates

Business Bay · Select Global Development L.L.C

CompletedLast site inspection February 12, 2026 · 9 months ago
100%complete

DLD first inspected the site on Jul 20, 2022 at 4.6% complete, and recorded it as finished after 10 inspections, the last on Feb 12, 2026.

First inspection · 4.6%Latest · 100%
Construction started
November 1, 2021
Completion date registered with DLD
September 1, 2024
Site inspections
10
Units
462
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2318

Latest site photos

February 12, 2026

Progress over time

Progress over time
0%25%50%75%100%2023202420252026

Inspection history

  1. February 12, 2026

    15 days after the previous inspection

    +1.3%100%
  2. January 28, 2026

    5 months after the previous inspection

    +3.2%98.7%
  3. August 27, 2025

    0 days after the previous inspection

    95.5%
  4. August 27, 2025

    6 months after the previous inspection

    +14.3%95.5%
  5. February 21, 2025

    4 months after the previous inspection

    +18.8%81.2%
  6. October 18, 2024

    3 months after the previous inspection

    +12.3%62.4%
  7. July 9, 2024

    5 months after the previous inspection

    +11.5%50.1%
  8. February 14, 2024

    6 months after the previous inspection

    +20.3%38.6%
  9. August 16, 2023

    13 months after the previous inspection

    +13.7%18.3%
  10. July 20, 2022

    First inspection

    4.6%

Thinking about Peninsula Two at Business Bay by Select Group?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2318), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat