Peninsula One at Business Bay, Dubai

Construction progress

Peninsula One at Business Bay, Dubai construction updates

Business Bay · Select Global Development L.L.C

CompletedLast site inspection August 6, 2025 · 15 months ago
100%complete

DLD first inspected the site on Jun 6, 2022 at 5.3% complete, and recorded it as finished after 7 inspections, the last on Aug 6, 2025.

First inspection · 5.3%Latest · 100%
Construction started
August 1, 2021
Completion date registered with DLD
April 1, 2024
Site inspections
7
Units
525
Buildings
2
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2284

Latest site photos

August 6, 2025

Progress over time

Progress over time
0%25%50%75%100%202320242025

Inspection history

  1. August 6, 2025

    5 months after the previous inspection

    +3%100%
  2. February 21, 2025

    4 months after the previous inspection

    +13.9%97%
  3. October 18, 2024

    3 months after the previous inspection

    +4%83.1%
  4. July 9, 2024

    4 months after the previous inspection

    +13.3%79%
  5. March 15, 2024

    6 months after the previous inspection

    +24.8%65.8%
  6. September 26, 2023

    16 months after the previous inspection

    +35.7%41%
  7. June 6, 2022

    First inspection

    5.3%

Thinking about Peninsula One at Business Bay, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2284), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.