Peninsula Five at Business Bay

Construction progress

Peninsula Five at Business Bay construction updates

Business Bay · Select Global Development L.L.C

CompletedLast site inspection January 13, 2025 · 2 years ago
100%complete

DLD first inspected the site on Oct 3, 2022 at 4.1% complete, and recorded it as finished after 5 inspections, the last on Jan 13, 2025.

First inspection · 4.1%Latest · 100%
Construction started
January 15, 2022
Completion date registered with DLD
December 15, 2024
Site inspections
5
Units
383
Buildings
3
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2344

Latest site photos

January 13, 2025

Progress over time

Progress over time
0%25%50%75%100%202320242025

Inspection history

  1. January 13, 2025

    6 months after the previous inspection

    +10.3%100%
  2. July 4, 2024

    3 months after the previous inspection

    +61%89.7%

    No photos were published for this inspection.

  3. March 27, 2024

    7 months after the previous inspection

    28.7%
  4. August 24, 2023

    11 months after the previous inspection

    +24.6%28.7%
  5. October 3, 2022

    First inspection

    4.1%

Thinking about Peninsula Five at Business Bay?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2344), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.