Pearl House 4 by Imtiaz at JVC, Dubai

Construction progress

Pearl House 4 by Imtiaz at JVC, Dubai construction updates

JVC · Imtiaz Luxury Real Estate Development L.L.C

Under constructionLast site inspection October 7, 2026 · 31 days ago
17.9%complete

When DLD first inspected the site on Sep 29, 2025, it was 0% complete. After 5 inspections it now stands at 17.9%.

That is about 1.5% more of the building completed each month on average.

First inspection · 0%Latest · 17.9%
Construction started
October 30, 2025
Completion date registered with DLD
February 29, 2028
Site inspections
5
Units
211
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
4129

Latest site photos

October 7, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 7, 2026

    3 months after the previous inspection

    +4.7%17.9%
  2. July 15, 2026

    3 months after the previous inspection

    +6.3%13.3%
  3. April 24, 2026

    3 months after the previous inspection

    +3.4%7%
  4. January 14, 2026

    4 months after the previous inspection

    +3.6%3.6%
  5. September 29, 2025

    First inspection

    0%

Thinking about Pearl House 4 by Imtiaz at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4129), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.