Pearl House 3 at JVC

Construction progress

Pearl House 3 at JVC construction updates

JVC · Imtiaz Ghd Real Estate Development L.L.C

CompletedLast site inspection April 23, 2026 · 7 months ago
100%complete

DLD first inspected the site on Jul 30, 2024 at 0% complete, and recorded it as finished after 7 inspections, the last on Apr 23, 2026.

First inspection · 0%Latest · 100%
Construction started
August 1, 2024
Completion date registered with DLD
August 1, 2026
Site inspections
7
Units
165
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3196

Latest site photos

April 23, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. April 23, 2026

    17 days after the previous inspection

    +0.4%100%
  2. April 6, 2026

    4 months after the previous inspection

    +19.5%99.6%
  3. December 15, 2025

    3 months after the previous inspection

    +28.8%80.2%
  4. September 12, 2025

    4 months after the previous inspection

    +19%51.4%
  5. May 27, 2025

    4 months after the previous inspection

    +21.7%32.4%
  6. January 13, 2025

    5 months after the previous inspection

    +10.7%10.7%
  7. July 30, 2024

    First inspection

    0%

Thinking about Pearl House 3 at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3196), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat