Pearl House 2 at JVC

Construction progress

Pearl House 2 at JVC construction updates

JVC · Imtiaz Real Estate Investment & Development L.L.C

CompletedLast site inspection October 15, 2025 · 13 months ago
100%complete

DLD first inspected the site on Sep 13, 2023 at 0% complete, and recorded it as finished after 6 inspections, the last on Oct 15, 2025.

First inspection · 0%Latest · 100%
Construction started
August 29, 2023
Site inspections
6
Units
202
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2777

Latest site photos

October 15, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. October 15, 2025

    4 months after the previous inspection

    +11.6%100%
  2. June 4, 2025

    4 months after the previous inspection

    +30.7%88.4%
  3. January 23, 2025

    5 months after the previous inspection

    +23.8%57.7%
  4. August 29, 2024

    6 months after the previous inspection

    +26.4%33.9%
  5. March 14, 2024

    6 months after the previous inspection

    +7.5%7.5%
  6. September 13, 2023

    First inspection

    0%

Thinking about Pearl House 2 at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2777), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat