Peace Lagoons at Dubailand

Construction progress

Peace Lagoons at Dubailand construction updates

Dubailand · Peace Homes Development L.L.C

Under constructionLast site inspection October 21, 2026 · 17 days ago
4.2%complete

When DLD first inspected the site on Jun 12, 2024, it was 0% complete. After 4 inspections it now stands at 4.2%.

That is about 0.1% more of the building completed each month on average.

First inspection · 0%Latest · 4.2%
Construction started
September 30, 2024
Completion date registered with DLD
September 30, 2028
Site inspections
4
Units
1,000
Escrow bank
Bank Of Sharjah
DLD project no.
3146

Latest site photos

October 21, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 21, 2026

    6 months after the previous inspection

    +1.3%4.2%
  2. April 23, 2026

    13 months after the previous inspection

    +2.6%2.9%
  3. March 19, 2025

    9 months after the previous inspection

    +0.3%0.3%
  4. June 12, 2024

    First inspection

    0%

Thinking about Peace Lagoons at Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3146), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.