Ozone 1 Residence at JVC

Construction progress

Ozone 1 Residence at JVC construction updates

JVC · Object One Real Estate Development L.L.C

Under constructionLast site inspection July 14, 2026 · 4 months ago
56.8%complete

When DLD first inspected the site on Mar 4, 2024, it was 0% complete. After 7 inspections it now stands at 56.8%.

That is about 2% more of the building completed each month on average.

First inspection · 0%Latest · 56.8%
Construction started
January 4, 2024
Site inspections
7
Units
272
Escrow bank
Abu Dhabi Islamic Bank
DLD project no.
2977

Latest site photos

July 14, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 14, 2026

    2 months after the previous inspection

    +3.1%56.8%
  2. May 7, 2026

    4 months after the previous inspection

    +6%53.8%
  3. December 24, 2025

    3 months after the previous inspection

    +8.8%47.7%
  4. September 23, 2025

    4 months after the previous inspection

    +11.6%38.9%
  5. June 3, 2025

    8 months after the previous inspection

    +16.8%27.3%
  6. October 10, 2024

    7 months after the previous inspection

    +10.5%10.5%
  7. March 4, 2024

    First inspection

    0%

Thinking about Ozone 1 Residence at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2977), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.