Oxford Terraces 2 at JVC, Dubai

Construction progress

Oxford Terraces 2 at JVC, Dubai construction updates

JVC · Iman Developers L.L.C

CompletedLast site inspection November 20, 2024 · 2 years ago
100%complete

DLD first inspected the site on Mar 6, 2023 at 2.1% complete, and recorded it as finished after 5 inspections, the last on Nov 20, 2024.

First inspection · 2.1%Latest · 100%
Construction started
February 15, 2023
Completion date registered with DLD
November 15, 2024
Site inspections
5
Units
101
Escrow bank
Mashreq Bank Psc
DLD project no.
2600

Latest site photos

November 20, 2024

Progress over time

Progress over time
0%25%50%75%100%2024

Inspection history

  1. November 20, 2024

    3 months after the previous inspection

    +15.2%100%
  2. August 29, 2024

    4 months after the previous inspection

    +27.5%84.8%
  3. May 1, 2024

    6 months after the previous inspection

    +25.8%57.3%
  4. November 14, 2023

    8 months after the previous inspection

    +29.4%31.5%
  5. March 6, 2023

    First inspection

    2.1%

Thinking about Oxford Terraces 2 at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2600), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.