Oxford Gardens at Arjan Dubai

Construction progress

Oxford Gardens at Arjan Dubai construction updates

Dubailand · Iman Developers L.L.C

CompletedLast site inspection September 22, 2025 · 14 months ago
100%complete

DLD first inspected the site on Aug 10, 2023 at 1.8% complete, and recorded it as finished after 5 inspections, the last on Sep 22, 2025.

First inspection · 1.8%Latest · 100%
Construction started
July 11, 2023
Completion date registered with DLD
March 30, 2025
Site inspections
5
Units
240
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2703

Latest site photos

September 22, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. September 22, 2025

    8 months after the previous inspection

    +29.1%100%
  2. January 13, 2025

    3 months after the previous inspection

    +25.7%70.9%
  3. October 1, 2024

    7 months after the previous inspection

    +29.2%45.2%
  4. March 13, 2024

    7 months after the previous inspection

    +14.2%16%
  5. August 10, 2023

    First inspection

    1.8%

Thinking about Oxford Gardens at Arjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2703), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.